Interlayer method ( cement mortar finish coat surfaces )

    1. Remove all objects, dust, and loose material from the construction surface.
    2. Coating of pipe edges, corners, and floor drains may be reinforced by adding 2-3 layers of single-component elastic cement.
    3. Apply one coat of single-component elastic cement diluted with 30% water as a primer and wait for 30 minutes before applying the next coat.
    4. Apply 2-3 coats of single-component elastic cement on the whole surface. Waterproofing layer for vertical walls in bathrooms should be applied to a height of at least 150cm.
    5. Upon application, allow a drying and curing time of 4-7 days prior to fitting of tiles or other stone materials.