Transparent and membranous dirt-resisting method for substrates such as elastic and cement paint.

    1. Remove or wash off all objects, dust, and loose material from the construction surface and allow a drying time of at least 3 days (construction surfaces must be completely dry to prevent a whitish appearance of coatings).
    2. Apply 2 thin coats of double-component anti-yellowing highly dirt-resistant transparent finish paint (stir thoroughly prior to application).
    3. If other coatings have just been applied to the surface, it must be ensured that such coatings are fully cured prior to application of this product (allow a curing time of at least 1 day).
    4. Upon mixing, the product must be applied within a period of around one hour. Depending on weather and temperature conditions, dirt-resistance effects appear after around 2-5 days.